On the grounds of the FAFC Went Building, which previously housed the departments of biology and pharmaceutics, an 18-story glass tower for the RIVM and the MEB is to be built. When dismantling buildings, the University of Utrecht has been committed to a sustainable execution since 2011. This also applied to the FAFC Went Building, whose building materials are reused or recycled as much as possible.
- Home
- all reference projects
- Expansion of Utrecht University
Expansion of Utrecht University, Netherlands
Major construction site
Customer |
MEET RIVM CBG B.V. |
Construction |
07/2017 to Q3 2021 |
A new location for the National Institute for Public Health and the Environment (RIVM) and the Medicines Evaluation Board (MEB)
The task
Since the National Institute for Public Health and the Environment works with devices that are very sensitive to vibrations, the architecture of the building has to comply to those needs. In this case, this led to considerable delays concerning the start of construction, as it was discovered that the original design of the building did not meet the requirements. Also, the construction itself is now more complex and will take a year longer than planned to complete.
A crane is to be built on each of the three building cores, that house the stairwells. Working from there, the cranes will erect the facade of the building. The cranes work in a confined space, but need relevant ranges to cover all areas of the building. Nevertheless, they must not get in each other's way.
A crane is to be built on each of the three building cores, that house the stairwells. Working from there, the cranes will erect the facade of the building. The cranes work in a confined space, but need relevant ranges to cover all areas of the building. Nevertheless, they must not get in each other's way.
The implementation
Luffing cranes are perfect for this type of operation because the movable jibs allow them to give each other space. Two WT 335L e.tronic and our new luffing crane WT 555L e.tronic are working on this construction site. The pictures show how the three cranes work from the stair towers. Completion is planned for autumn 2021.
WILBERT Project References
- All
- all reference projects
- large construction sites
- special projects
- structural engineering
- bridges and tunnels
- power plants
Replacement Bridge Strombrückenzug, Magdeburg (DE)
Our allrounder crane WT 260 e.tronic works at the central pylon of the bridge that is going to cross the Zollelbe and the Alte Elbe in Magdeburg. With its fast work speeds it is ensuring that everything works smoothly on the builiding site.
Police Headquarters Osthessen, Offenbach (DE)
A new era is dawning for the police in Osthessen. Five WT 650 e.tronic are needed to span the major construction site of the new headquarters that will house 11 departments and 900 officers.
Specialised Crane at Grand Tower, Frankfurt
At Grand Tower in Frankfurt, the facade and the balconies/loggias are attached currently. This task was taken on by a WILBERT specialised crane mounted on the roof of the building.
JaBee Tower, Dübendorf (CH)
The highest residential tower in Switzerland is being built in Dübendorf near Zurich. Five commercial premises on the ground floor and 218 rental apartments are distributed over a tower height of 100 m. Due to the proximity to the airport, the crane was dismantled at night after the suspension of flight operations.
Deconstruction of Deutsche Bank IBCF, Frankfurt
On the former Deutsche Bank site, the old buildings had to make room for a building complex of four high-rise towers, the Quartier Four, that is planned to be completed in 2023.
Pont du Lanciau, Rossinière
Reconstruction of the Pont du Lanciau: demanding work due to the cramped, hilly terrain and a tandem lift with a mobile crane.
Grand Tower, Frankfurt
There's a webcam where you can live view the construction of Germany's tallest residential tower and our two WT 420 e.tronic on site.
Marienturm, Frankfurt
The construction progress of the Marienturm, a new office tower in Frankfurt's banking district, can be viewed live via webcam. Two WT 335L e.tronic cranes from our rental fleet are involved in this project.
Solar Tower Ouarzazate, Morocco
The steel components of the absorber have a maximum weight of 90 t and were lifted to the top of the 240 m solar tower by our WT 2405L e.tronic.
Ruhr West University of Applied Sciences, Mülheim
HWR’s new campus was built on an area of approx. 40,000 m² between September 2012 and December 2015. Four WILBERT trolley cranes were used: 3× WT 200 e.tronic and 1× WT 320 e.tronic.
REA Turow, Bogatynia (PL)
Here, the task of the WT 2405L e.tronic was the chimney modernisation in a densely built-up area: The existing filters had to be replaced by new, better performing filters at dizzying heights. The crane was assembled at a low height and then erected by crawling for this purpose.
Housing Development Feuerbachstraße, Frankfurt
A residential complex comprising 126 luxury apartments and an underground garage with 220 parking spaces was built in Feuerbachstraße in Frankfurt. Construction was completed in 2015. Four WILBERT cranes were used: 2× WT 150 e.tronics and 2× WT 200 e.tronics.
OpernTurm, Frankfurt
The 170m skyscraper was completed in spring 2016 and comprises an impressive 62,500 m² of usable space on 42 storeys. During the construction phase, two WT 300 e.tronics and one WT 205L e.tronic were used.
Grain Storage Silos, Brake
38 honeycomb-shaped silos in total measuring 61 m in length, 22 m in width and 83 m in height were erected in the port of Brake, Germany, by a WT 200 e.tronic and a WT 300 e.tronic using the slip-form method.
Alpha Rotex in Gateway Gardens, Frankfurt
At 66 m and 16 storeys, Alpha Rotex is the tallest building right at the airport. A WT 300 e.tronic, a WT 200 e.tronic and a WT 180 were involved. A height limit had to be observed due to the building’s proximity to the airport.
- 1
- 2